Project. Commissioning. Production.

Commissioning industrial equipment

From an installed machine to stable production.

More than starting a PLC program. I check equipment, signals, drives, industrial communication and control logic step by step — through to stable automatic operation.

Project engineering, my own software and commissioning as one connected technical task.

Roller conveyors and packaging machine on the chipboard line in Izhevsk, Case 003
Izhevsk · packaging line · Case 003
Project and software
Checks on the installation
Production and handover

01 / Starting point

Where does your installation stand?

  1. Installation completeThe equipment is not running yet

    The cabinet, electrical equipment and hardware are installed. Their interaction now needs to be checked.

  2. New control systemReady for the first start

    PLC, HMI, drives and signals need to become one functioning system.

  3. After modernizationStable automatic operation is the goal

    The updated technology must work together with existing assemblies and the process.

02 / The start-up sequence

How commissioning works

From the initial information to individual functions, then to the automatic cycle. Each stage creates the basis for the next.

Packaging-line control cabinet with Siemens PLC, terminals, relays and drives
Control cabinet of the Izhevsk line. PLC, signals and drives are checked as one system.

Checks and the start-up sequence are agreed for the conditions of each installation.

  1. Preparation

    Review electrical drawings, equipment, project structure, parameters and initial information.

  2. Signal checks

    Check sensors, actuators, limit switches, valves, feedback signals and electrical logic.

  3. Drives and communication

    Check frequency drives, PROFINET / PROFIBUS / Modbus / CAN and communication between components.

  4. Manual operation

    Check individual equipment functions and assemblies step by step.

  5. Automatic operation

    Set up sequences, interlocks, transitions and process logic.

  6. Optimization

    Adjust parameters, timing, operating logic and diagnostic messages.

  7. Handover to operation

    Final checks, backup, documentation and handover to the customer.

03 / Technical scope

What commissioning includes

The installation is at the centre. Software, electrical equipment, drives and the operator interface need to work together.

Chipboard packages transported on the conveyors of an automatic packaging line
One installation. Shared control logic.

PLC / Siemens

Program, states, interlocks and interaction between assemblies.

HMI / SCADA

Operator screens, messages, recipes and PLC data exchange.

Drives and servo

Parameters, commands, feedback and motion functions.

Sensors and actuators

Inputs, outputs, limit switches, valves and feedback.

Industrial communication

Networks and interfaces specified in the installation project.

Automatic control logic

Sequences, transitions and coordinated line operation.

Optimization and handover

Settings, software versions, documentation and staff instruction.

The result matters after start-up, too

A running installation.
A clear handover.

I make time not only for start-up, but also for what stays with the customer: up-to-date drawings, software, a backup, instructions and an explanation of the system. The documentation scope is agreed for the project.

  • Current software versions and a backup
  • Electrical drawings and operating instructions
  • Instruction for operators and maintenance staff

04 / Real start-ups

Proven on the production floor

Two projects where software, equipment and commissioning were part of one engineering task.

Conveyors and turntable of the chipboard packaging line in IzhevskCase 003

Complete development and start-up

Packaging line in Izhevsk

Siemens S7-1215 · 7″ HMI · PROFINET

Task
Develop a control system for automatic transport and packaging of chipboard bundles using the customer’s specification and drawings.
Work
PLC/HMI development, installation support, mechanism checks and commissioning of all operating modes.
Result
The customer accepted the line; automatic operation is stable, and documentation and operator instructions were handed over.
Learn more
12-ton harbour crane from the modernization project in BatumiCase 001

Modernization and drive commissioning

12-ton harbour crane

5 drives · Emotron · STEP 7

Task
Replace obsolete Mannesmann drives for which spare parts were no longer available.
Work
Adapt drawings and STEP 7, integrate and parameterize the new drives, and commission the crane on site.
Result
The crane was modernized and put into operation; provision was made for remote diagnostics.
Learn more

05 / Before the start

What helps with preparation

Initial information helps us understand the task sooner and agree how to prepare for start-up.

  • Electrical drawings
  • PLC / HMI project
  • Signal / I/O list
  • Drive data
  • Equipment photos
  • Network structure
  • Preferred start-up date

Even if not everything is ready yet, we can discuss the task in advance.

1 yearof remote support

After commissioning

Start on site.
Continue support remotely.

After start-up, questions, diagnostics and agreed minor adjustments can be handled remotely where suitable access is available.

For installations programmed and commissioned by Poljakov Automation, one year of remote support is provided where suitable access is available. Scope and conditions follow the project offer; this does not mean unlimited extensions or a warranty for third-party hardware.

More about remote support

FAQ

Before the first start

Can programming and commissioning be part of one project?

Yes. The main approach is to take my own project engineering and PLC/HMI software through commissioning, automatic operation and customer handover.

What if some documentation is still missing?

We can start by discussing the current situation. Drawings, PLC/HMI projects, equipment data and the preferred start-up date help identify what still needs to be prepared.

Is staff instruction included?

During handover, I explain the system’s operation to operators and maintenance personnel. Instruction and documentation are included in the agreed project scope.

Is support available after start-up?

Yes, with suitable remote access. One year of support is provided for installations I program and commission; the project offer defines the scope and conditions.

From project to a functioning system

Ready for the first start?

Commissioning is the moment a project has to become a real working system. If the equipment is ready to start or needs support through to stable automatic operation, simply describe the current situation.

I will review the initial information and suggest an appropriate way of working.